Bozeat Parish Council – Highways Monthly Report APPENDIX C
Month ending 12th September 2022
Street Doctor Headline
No new street doctor reports raised during this period. Report 119 has been completed. The following remain open and continue to be monitored Boz 99 and 116.
The current position with the matters raised with NNC representative is as follows:
Request made to Ian Boyes to install, as per email; road markings and signs so described. No change.
Notes from meeting with Ben Wright held on the 3rd August 2022.
Removal of hedge at the corner of Allens Hill and London Road. To facilitate yield sign replacement; chase up removal’ Response from Highways: This will be removed on Friday 5th Hedge has been removed and work to replace the yield sign has been programmed for October 2022.
Lowering of the kerb at the corner of Harrold Road and Church Lane to be completed prior to the school returning from summer break; we agreed the importance of meeting this deadline; to be brought to the attention of relevant team undertaking the work to ensure it is completed on time. Response from Highways: Works will be undertaken over the school holiday period as discussed on site. This work has been completed.
The vegetation obscuring road sign along Church Lane to be trimmed back; currently not visible. Response from Highways: A works order is being raised to clear this vegetation within 28 days. This work has been completed.
The junction of Harrold Rd and Church Lane/Allens Hill. Marked up for thermal repair work. Response from Highways: The Thermal Repairs will be added to our existing order that will be completed within the next 6 months. No change.
Harrold Rd and Dychurch Lane Street signs to be replaced. Response from Highways: This issue has been referred to NNC who maintain street nameplates – I’ll report back any updates. No change.
NNC to review the roads in Bozeat before October this year for surface dressing; for inclusion in next years’ programme of works. Highways have put the suggested sites forward to the team responsible for surface treatments and will have a programme around October-time. It must be noted that these sites aren’t guaranteed for inclusion in the programme and will be ranked alongside other recommended sites across North Northamptonshire. Provide feedback on whether Bozeat roads are to be sealed. Response – Still awaiting firm programme from the team responsible and will update as soon as I have confirmation. No change.
Pavement areas along Abbey Close and the corner of Queen Street and Easton Lane have been identified for repair. No change.